红水河Issue(6):42-44,3.
厂房上游启闭机右侧悬挑平台排架优化施工
Plant upstream hoist right cantilever platform optimization of construction
谭伟军 1梁梅芳1
作者信息
- 1. 广西水电工程局,广西 南宁 530001
- 折叠
摘要
Abstract
The paper makes an introduction to the construction optimization scheme for cantilever platform bent frame on the right of powerhouse upstream hoist of the extension project of Bagong hydropower station. The optimization scheme shortens the construction period and saves the project cost through precise calculation and effective measures corresponding to the actual situations and characteristics of the project.关键词
启闭机/悬挑平台/排架/拔贡水电站改扩建工程Key words
hoist/cantilevered platform/bent frame/Extension Project of Bagong Hydropower Station分类
建筑与水利引用本文复制引用
谭伟军,梁梅芳..厂房上游启闭机右侧悬挑平台排架优化施工[J].红水河,2013,(6):42-44,3.