摘要
Abstract
Constrained by the current construction conditions and the requirements for overall construction progress, part of high-filled canal of Middle Route Project of South-to-North Water Diversion is difficult to meet the demand of more than six-month pre-settling time. In view of the actual situation of the typical section of high-filled canal, the impact of settlement deformation after construction on stress distribution, flexural deformation of concrete slab is analyzed in detail. Moreover, the pa-per proposes the control measures of settlement deformation according to the research results, which provides technical reference for the water-filling test and normal safe operation of the high-filled canal.关键词
高填方渠坡/衬砌面板/沉降变形/南水北调中线工程Key words
high-filled canal slope/concrete slab/settlement deformation/Middle Route Project of South-to-North Water Diversion分类
建筑与水利