西北水电Issue(6):97-100,4.
小湾水电站导流洞下闸施工技术
Construction Technology for Gate Closing of Diversion Tunnel, Xiaowan Hydropower Project
张智1
作者信息
- 1. 中国水利水电建设工程咨询西北公司小湾监理中心,西安 710075
- 折叠
摘要
Abstract
Before the diversion tunnel of Xiaowan Hydropower Project is gated.Exploration under water is executed twice.The suitable scheme for gate closing and leakage blocking is finalized after the actual conditions of sills and slots are made clear.Full exercises are performed before the gate is closed so that all participants well acknowledge the closing flow to assure the smooth gate closing operation. Leakage behind the gate is blocked in time based on the actual leakage after the gate is closed.Application of concrete placement under water for the leakage blocking achieves excellently .关键词
小湾/导流洞/下闸/技术Key words
Xiaowan/diversion tunnel/gate closing/technology分类
建筑与水利引用本文复制引用
张智..小湾水电站导流洞下闸施工技术[J].西北水电,2013,(6):97-100,4.