Abstract
Through the analysis of the causes to the failure of trashrack at initial impoundment, Jishixia Hydropower Project, issues on the trashrack initially operating at lower water level are raised.关键词
拦污栅/低水位运行/破坏/漩涡/积石峡水电站Key words
trashrack/operation at low level/failure/vortex/Jishixia Hydropower Project分类
建筑与水利引用本文复制引用