压力容器Issue(11):62-69,75,9.DOI:10.3969/j.issn.1001-4837.2013.11.011
AP1000反应堆冷却剂系统主要设备安装技术
Installation of Main Equipments of Reactor Coolant System in AP1000 Nuclear Power Plant
左学兵 1陈晶晶 1张金东 1代帅 1郑东宏1
作者信息
- 1. 国核工程有限公司,山东 海阳 265116
- 折叠
摘要
Abstract
The installation format and technical requirements of main equipments were established on the basis of the function and consists of the reactor coolant system.Combined with their own characteristics of advanced passive PWR(AP1000),the installation logic and sequence of reactor vessel,reactor coolant line,steam generator,reactor coolant pump,pressurizer and surge line are fully description hereafter.And in the practice of Haiyang Nuclear Power Plan,it can be used as a guideline for the installation of nuclear steam supply system of the coming project.关键词
AP1000/反应堆冷却剂系统/压力容器/蒸汽发生器/安装Key words
AP1000/reactor coolant system/reactor vessel/steam generator/installation分类
机械制造引用本文复制引用
左学兵,陈晶晶,张金东,代帅,郑东宏..AP1000反应堆冷却剂系统主要设备安装技术[J].压力容器,2013,(11):62-69,75,9.