中国科技投资Issue(6):4-6,7,4.
茅台大桥改建总体方案研究与设计
Research(and(Design(on(the(General((Reconstruction Plan(of(Maotai(Bridge
殷伟 1高磊2
作者信息
- 1. 中交第一公路勘察设计研究院有限公司
- 2. 云南省交通规划设计研究院
- 折叠
摘要
Abstract
In this paper, based on the present situation and the environment characteristics of Maotai Bridge, Introduced the comparison and recommendation of design options for the general reconstruction plan of Maotai Bridge.Conformed the final plan that is buiding theauxiliary bridge of bailey beam、demolishing the old bridge、constructing the new bridge of continuous beams with variable section on the formerly position.The spans of new bridge is 3×20m+58m+100m+58m, 284.5m total length.关键词
茅台大桥/便桥/改建方案/变截面连续梁Key words
Maotai Bridge/Auxiliary Bridge/reconstruction plan/continuous beams with variable section引用本文复制引用
殷伟,高磊..茅台大桥改建总体方案研究与设计[J].中国科技投资,2014,(6):4-6,7,4.