The paper summarizes the upgrade transformation of differential protection of busbar due to exten-sion of duplicate-busbar to duplicate-busbar single-segmentation in extension project of the newly-added main transformer 3# in 220 kV substation. It lays emphasis on correspondence of the primary and secondary physi-cal wiring position and indicates precautions in transformation of differential protection of busbar, which can provide reference for relevant projects.

关键词

母线差动保护/变电站/双母线单分段/升级改造

Key words

busbar differential protection/substation/duplicate-bus single-segmentation/upgrade transfor-mation