城市建筑Issue(12):395-396,2.
台山核电站燃料厂房内屋面预制板吊装管理
The Hoisting Management of the Interior Roof Precast Slabin the Fuel Plant of Taishan Nuclear Power Station
周安清1
作者信息
- 1. 中国核工业华兴建设有限公司,南京210019
- 折叠
摘要
Abstract
This paper introduces the hoisting equipment and rigging of the large roof precast slab of Taishan EPR nuclear fuel plant, and the hoisting management of whole process, hoi-sting safety control, emergency plan, instalation quality con-trol.关键词
预制板/吊装/管理Key words
prefabricated panels/lifting/management引用本文复制引用
周安清..台山核电站燃料厂房内屋面预制板吊装管理[J].城市建筑,2014,(12):395-396,2.