| 注册
首页|期刊导航|广西水利水电|马马崖一级水电站折线坝坝顶变形监测设计

马马崖一级水电站折线坝坝顶变形监测设计

邓荣欢 龚刚

广西水利水电Issue(6):89-91,96,4.
广西水利水电Issue(6):89-91,96,4.

马马崖一级水电站折线坝坝顶变形监测设计

Crest deformation monitoring design for zigzag-axis main dam of Mamaya Cascade-I Hydropower Project

邓荣欢 1龚刚1

作者信息

  • 1. 中国电建集团贵阳勘测设计研究院有限公司,贵州 贵阳 550081
  • 折叠

摘要

Abstract

The main dam of Mamaya Cascade-I Hydropower Project is designed with zigzag axis,rendering much limitations for arrangement of crest deformation monitoring equipment. Therefore,the structure and arrangement of surface monitoring piers were improved; hydrostatic leveling system was adopted for calibration of vacuum laser alignment system,which properly solved the crest deformation monitoring problem for zigzag-axis dam and may be reference for similar projects.

关键词

折线坝/变形监测/坝顶/马马崖一级水电站工程

Key words

Zigzag-axis dam/deformation monitoring/dam crest/Mamaya Cascade-I Hydropower Project

分类

建筑与水利

引用本文复制引用

邓荣欢,龚刚..马马崖一级水电站折线坝坝顶变形监测设计[J].广西水利水电,2014,(6):89-91,96,4.

广西水利水电

1003-1510

访问量0
|
下载量0
段落导航相关论文