结构工程师Issue(4):147-154,8.
轮式预应力钢结构施工模拟方法研究
Construction Simulation Method of Pre-stressed Wheel Steel Structure
摘要
Abstract
With the development of construction technology,construction methods with rigid body rotation is making progress continuously,bringing challenges to construction simulation technology not only in simulating the construction process with a lot of members,but also in simulating the construction process with increased and moved members.This paper is based on the vertical rotation construction method of Beijing Great Wheel. According to the nonlinear finite element method,the expansion and modification method of the displacement matrix,load matrix and tangent stiffness matrix after rigid body rotation are proposed,providing theoretical ba-sis for new construction simulation method for construction process with rigid body rotation;Based on the mod-eling by step method,combined with the application of finite element software ANSYS,a new construction simulation method named as the coordinate rotation method based on modeling by step is proposed.The validi-ty of this method is verified by examples.关键词
摩天轮/施工模拟/竖立旋转法/分步建模法/基于分步建模的坐标旋转法Key words
ferris wheel/construction simulation/vertical rotation method/modeling by step method/coordi-nate rotation method based on modeling by step method引用本文复制引用
罗永峰,白洁,贾宝荣,陈晓明..轮式预应力钢结构施工模拟方法研究[J].结构工程师,2014,(4):147-154,8.基金项目
国家自然科学基金资助项目 ()