Anew technology in hydraulic pressure was introduced,w hich tellhow to design the clam ping ofthe hydraulic test m oulds from outside to im prove the technology ofthe hydraulic testand working efficiency,and reduce the working process. Then itisnotnecessary to rem ain the hydraulic pressure m argin during the hydraulic testofw ater-w allofthe header.The butt groove should be machined directly according to the size of the draw ings to sim plify the working process and reduce the costs.The technology was proved by practices and deserved to popularize for academ ic reference.关键词
管屏/集箱/水压试验/水压试验工装Key words
platen superheater/header/hydrostatic pressure/hydrostatic pressure equipm ent分类