| 注册
首页|期刊导航|南水北调与水利科技|丹江口水库陶岔渠首枢纽工程地基渗控处理

丹江口水库陶岔渠首枢纽工程地基渗控处理

奚建猛 孙业文 龚志明

南水北调与水利科技Issue(3):205-208,4.
南水北调与水利科技Issue(3):205-208,4.DOI:10.13476/j.cnki.nsbdqk.2014.03.045

丹江口水库陶岔渠首枢纽工程地基渗控处理

Seepage Control Treatment of Dam Base in Pivotal Project of Taocha Canal Headwork of Danjiangkou Reservoir

奚建猛 1孙业文 2龚志明1

作者信息

  • 1. 盐城市河海工程建设监理中心,江苏 盐城 224002
  • 2. 淮河水利委员会 治淮工程建设管理局,安徽 蚌埠233001
  • 折叠

摘要

Abstract

When the water level is high in the Danjiangkou Reservoir, the following problems occur in its accessory dam - the pivotal project of Taocha Canal H eadw ork, such as seepage in the dam base and around the dam, therefore the seepage control treatment needs to be conducted to the dam base and dam foundation. Based on the field curtain grouting experiment and the project characteristics, a reasonable seepage control treatment design and construction scheme for dam base w as proposed, w hich can solve the follow ing problems including drilling holes in deep overburden layers, burying and covering up grout nipple, grou2 ting at the contact face between the land and rock,and curtain grouting to thehighly permeablekarst rock mass under thedeep overburdenlayers.Afterthecompletionoftheseepagecontroltreatmentfordambase,thequalityandsafetyoftheprojectwere investigated, and the results showed that the seepage control treatment for dam base in the pivotal project of Taocha Canal Headwork meets the design requirements and achieves the desired results. The field curtain grouting experiment method, and design and construction scheme can provide reference for solving similar problems of seepage control of deep overburden layers.

关键词

陶岔渠首/渗控处理/帷幕灌浆/深厚覆盖层

Key words

T-aocha-Canal-Headwork/seepage-control-treatment/curtain-grouting/deep-overburden-layer

分类

建筑与水利

引用本文复制引用

奚建猛,孙业文,龚志明..丹江口水库陶岔渠首枢纽工程地基渗控处理[J].南水北调与水利科技,2014,(3):205-208,4.

南水北调与水利科技

OA北大核心CSCDCSTPCD

2096-8086

访问量0
|
下载量0
段落导航相关论文