南水北调中线工程禹州-长葛段建设管理

徐庆河

人民长江Issue(10):1-3,3.
人民长江Issue(10):1-3,3.

南水北调中线工程禹州-长葛段建设管理

Construction management of Yuzhou-Changge section of Middle Route Project of South to North Water Diversion Project

徐庆河1

作者信息

  • 1. 河南省南水北调中线工程建设管理局 许昌建管处,河南 郑州450003
  • 折叠

摘要

Abstract

Yuzhou-Changge section of Middle Route Project of South to North Water Diversion Project, with a total length of 53. 7 km and 99 various structures distributed, is located in a transition zone of Sanfengshan hilly areas and plains. To ensure the construction quality of the canal passing through collapsible loess area, expansive rock ( soil) area and a coal mined-out area in the practical construction process, the design departments had adjusted, modified and optimized the original solution according to engineering geological conditions, so that the major geological problems can be properly tackled. Furthermore, the institutional system, management practices as well as treating process of main geological challenges are elaborated in detail.

关键词

建设管理体系/基础处理/膨胀岩(土)/煤矿采空区/南水北调中线工程

Key words

management system/foundation treatment/expansive rock (soil)/coal mined-out area/Middle Route Project of South to North Water Diversion Project