Stage II cofferdam seepage prevention wall of Zhentouba I Hydropower Station is characterized as large construction quantity and tight construction period. In order to ensure flood season safety and smooth construction of follow-up construction, the construction and management units carried out fine management on the construction of stage II cofferdam seepage prevention wall, made out the measures mainly in 2 aspects of construction quality and progress control, and in the management, focused on 6 aspects of foresight consciousness, construction node control, quality assurance, civilized construction, capital assurance, tech-nology implement. For strictly implementing fine management, stage II cofferdam seepage prevention wall was completed with high quality and 10 days ahead of schedule.关键词