人民长江Issue(2):40-43,4.DOI:10.16232/j.cnki.1001-4179.2015.02.010
向家坝水电站左岸高边坡开挖与支护施工技术
Construction technology of excavation and supporting of high slope at left bank of Xiangjiaba Hydropower Station
樊凯1
作者信息
- 1. 中国长江三峡集团公司向家坝工程建设部,四川宜宾644600
- 折叠
摘要
Abstract
The layout of hydro -complex of Xiangjiaba Hydropower Station is constrained by the topographic condition , the mountain body at left bank should be excavated for the layout of stage II diversion structure , upstream and lower stream approach channels of ship lift.The geological condition of the high slope formed by the excavation is complicated ;in addition, the mined-out area and coal holes exist , which are the main influential factors for the local safety of the slope .To ensure the stability of the high slope and the safety of the hydro -complex, reinforcement measures should be adopted .Through researches, the con-ventional support measures such as anchor cable and anchor rod are taken , and the mined-out area and coal holes are filled . The monitoring after the treatment shows that the high slope is in a stable state .关键词
高边坡/煤层采空区/边坡开挖/支护工程/向家坝水电站Key words
high slope/mined-out area/slope excavation/supporting project/Xiangjiaba Hydropower Station分类
天文与地球科学引用本文复制引用
樊凯..向家坝水电站左岸高边坡开挖与支护施工技术[J].人民长江,2015,(2):40-43,4.