人民长江2015,Vol.46Issue(10):87-90,4.DOI:10.16232/j.cnki.1001-4179.2015.10.021
某混凝土重力坝前倾现象成因分析
Cause analysis of lean-forward phenomenon of a concrete gravity dam
陶丛丛 1吴波 1宋永占1
作者信息
- 1. 国网电力科学研究院,江苏 南京211100
- 折叠
摘要
Abstract
The prototype monitoring data of a concrete gravity dam in Southeast China shows that the dam body and dam foun-dation at the left bank is leaning toward the upstream direction. The qualitative and quantitative analysis results by using different analytical methods such as comprehensive process line contrast and mathematical modelling demonstrate that the leaning phenom-enon is real and the underlying cause is the sedimentation in front of dam. The bedrock of dam foundation at left bank is weak, and the sedimentation year by year in the front of the dam weights the bottom of reservoir, causing the sink of the upstream reser-voir base. The sedimentation phenomenon should be focused, and the effect of the sedimentation on the dam deserves further study.关键词
混凝土重力坝/大坝前倾/成因分析/坝前淤积Key words
concrete gravity dam/lean-foreard phenomenon of dam/cause analysis/sedimentation in front of dam分类
建筑与水利引用本文复制引用
陶丛丛,吴波,宋永占..某混凝土重力坝前倾现象成因分析[J].人民长江,2015,46(10):87-90,4.