云南大盈江四级水电站泥沙处理措施及效果分析
Measures for sediment treatment of Dayingjiang Hydropower Station IV in Yunnan Province and effect analysis
洪世兴 1邱本军 2曲德威3
作者信息
- 1. 云南省水利水电建设管理与质量安全中心,云南 昆明650224
- 2. 云南省大理州水利水电工程建设质量与安全监督站,云南 大理671000
- 3. 云南省盈江县多源水电开发公司,云南 盈江679300
- 折叠
摘要
Abstract
The reservoir storage of Dayingjiang Hydropower Station IV in Yunnan Province is small, so the sediment can not be regulated effectively. The sediment erosion resulted in serious damage to the hydraulic turbine generator in only one flood season after the operation. The design units carried out a special research and proposed to add a sediment settling treatment pool to the water power system. After the operation of the pool, the sediment amount and sediment gradation at the water intake and tail wa-ter were compared, and the sedimentation ratio, sediment grain in the pool were analyzed as well. The analysis results showed that the sedimentation of the pool was effective, which reduced the sediment passing through the turbine and mitigated the abra-sion of the turbine. No obvious abrasion was discovered during the check of the overflow parts, which have realized high effective operation of the turbine unit.关键词
泥沙磨损/沉沙池/水轮发电机组/大盈江四级水电站Key words
sediment abrasion/sediment pool/hydraulic turbine generator unit/Dayingjiang hydropower station IV分类