| 注册
首页|期刊导航|人民黄河|陡深斜井自密实混凝土衬砌施工技术

陡深斜井自密实混凝土衬砌施工技术

王国伟 侍克斌 白现军 努尔开力·依孜特罗甫

人民黄河Issue(9):130-133,4.
人民黄河Issue(9):130-133,4.DOI:10.3969/j.issn.1000-1379.2014.09.041

陡深斜井自密实混凝土衬砌施工技术

Steep Slope of Self Compacting Concrete Lining Construction Technology

王国伟 1侍克斌 1白现军 2努尔开力·依孜特罗甫1

作者信息

  • 1. 新疆农业大学水利与土木工程学院,新疆乌鲁木齐830052
  • 2. 葛洲坝新疆工程局 有限公司,新疆乌鲁木齐830049
  • 折叠

摘要

Abstract

In the construction of steep deep inclined shaft in Bulungkol-Gongur Hydropower Station mix proportion of the high performance concrete was adjusted because of the problems that difficult artificial vibration and easily blocked pipe and slow construction caused by large inclined angle and long distance concrete slip and the pouring concrete and steel pipe installation required to constantly turn. It finally got a grade pump pouring smooth,vibration free,fast and continuous construction self compacting concrete;by increasing the length of the segmented pouring (usually 80 m, the longest one was 110m),in the slide tube within the entire feeding process without any slow falling device measures,it thus simiplified the con-struction process,reduced the construction difficulty and improved the efficiency of the construction.

关键词

陡深斜井/衬砌施工/自密实混凝土/布仑口-公格尔水电站

Key words

steep deep inclined shaft/lining construction/self compacting concrete/Bulungkol-Gongur Hydropower Station

分类

建筑与水利

引用本文复制引用

王国伟,侍克斌,白现军,努尔开力·依孜特罗甫..陡深斜井自密实混凝土衬砌施工技术[J].人民黄河,2014,(9):130-133,4.

基金项目

新疆科技支撑计划项目(201233132);新疆水利水电工程重点学科基金资助项目(XJzdxk-2010-02-12)。 ()

人民黄河

OA北大核心

1000-1379

访问量0
|
下载量0
段落导航相关论文