Abstract
Based on the planar mesh generation of general arrangement plan and typical sections,combined with the linear interpolation of control sections,the automatic division of 3D FEM mesh for large scale underground caverns’seepage analysis was realized by means of the super-element method under complicated geological conditions. This method contributed a solution for the problems caused by the complex boundaries,polytropic strata materials and the saltation of the buildings. Several engineering applications show that this method is more simple,applicable and efficient.关键词
超单元网格法/三维有限元/建模/大型地下洞室群Key words
super-element method/3D FEM/modeling/large scale underground caverns分类