河口村水电站水轮机选型设计

张新伟 毛艳民 沈珊珊

人民黄河Issue(12):104-106,3.
人民黄河Issue(12):104-106,3.DOI:10.3969/j.issn.1000-1379.2014.12.033

河口村水电站水轮机选型设计

Type Selection of Hydraulic Turbine for Hekoucun Hydropower Station

张新伟 1毛艳民 1沈珊珊1

作者信息

  • 1. 黄河勘测规划设计有限公司,河南郑州450003
  • 折叠

摘要

Abstract

There are two hydropower stations in Hekoucun hydropower project. The operation range of water head,setting elevation,unit layout of these two stations are different. According to the characteristics of layout and water head,through comprehensive comparisons and analysis of model parameter,the turbine type and main parameter were determined;combining with the factors of performance of economy and technology,operation flexible and etc. ,the number and type of units were selected rationally,which guaranteed the station operation steady and safety.

关键词

水轮机/选型设计/卧式机组/混流式水轮机/河口村水电站

Key words

turbine/turbine type selection/horizontal unit/francis turbine/Hekoucun Hydropower Station

分类

建筑与水利

引用本文复制引用

张新伟,毛艳民,沈珊珊..河口村水电站水轮机选型设计[J].人民黄河,2014,(12):104-106,3.

人民黄河

OA北大核心

1000-1379

访问量0
|
下载量0
段落导航相关论文