过较大断层时综掘机行走方式研究

陆继旺 侯照东 高亚洲

山东煤炭科技Issue(8):25-26,2.
山东煤炭科技Issue(8):25-26,2.DOI:10.3969/j.issn.1005-2801.2014.08.12

过较大断层时综掘机行走方式研究

Study and Application of roadheader walking method crossing large fault

陆继旺 1侯照东 1高亚洲1

作者信息

  • 1. 永煤集团新桥煤矿,河南 永城 476600
  • 折叠

摘要

Abstract

Using backing plate under the roadheader rear crawler to increase friction between the bottom and the track to make roadheader forward;while larger slope, taking the rope with the scraper conveyor chain and connect ring ifxed the anchor and the large cylinder of cutting head together, by retracting the cutting head of cylinders to tension wire rope and chain to walk forward;another by changing the cut line boring machine, boring machine to better avoid falling back, successfully passed the DF24 normal faults.

关键词

掘进机/大倾角/行走

Key words

roadheader/big dip/walk