| 注册
首页|期刊导航|水力发电|光照水电站大坝基础处理设计探讨

光照水电站大坝基础处理设计探讨

焦雪梅 雷声军 陈毅峰 单承康

水力发电Issue(12):48-50,58,4.
水力发电Issue(12):48-50,58,4.

光照水电站大坝基础处理设计探讨

Discussion on the Design of Dam Foundation Treatment of Guangzhao Hydropower Station

焦雪梅 1雷声军 2陈毅峰 2单承康2

作者信息

  • 1. 中国水电工程顾问集团有限公司,北京 100120
  • 2. 中国电建集团贵阳勘测设计研究院有限公司,贵州 贵阳 550081
  • 折叠

摘要

Abstract

The carrying capacity of foundation and the seepage control of curtains in left and right banks are important part of the design of dam foundation treatment of the RCC gravity dam in Guangzhao Hydropower Station. Combined with the actual situation, the innovative design ideas are proposed to accelerate the construction of dam, including carried out consolidation grouting of dam foundation between two compacted layer construction, determining foundation rock conditions by using two criteria of the permeability ratio of grouting hole not more than 1 Lu achieved by simple water pressure test before grouting and the grout consumption of grouted hole not more than 40 kg/m, and increasing the depth of grouting holes in some area. These innovative design ideas have accelerated the speed and improved the quality of dam construction.

关键词

碾压混凝土重力坝/基础处理/设计/光照水电站

Key words

roller compacted concrete gravity dam/foundation treatment/design/Guangzhao Hydropower Station