铁道标准设计Issue(6):76-82,83,8.DOI:10.13238/j.issn.1004-2954.2014.06.018
带副拱中承式菱形变截面钢管混凝土系杆拱桥主拱肋安装技术
Installation Technology for Main Arch Rib of a Concrete-filled Steel Tubular Half-through Tied-arch Bridge with Vice Arch and Rhombic Variable Cross-section
摘要
Abstract
This paper was based on the construction of main bridge of the Wuhu Yuanze Bridge, the first one in China in the form of concrete-filled steel tubular half-through tied-arch bridge with vice arch and rhombic variable cross-section. This paper expounded the installation technology of the main arch rib of this bridge, mainly including how to install the main arch rib, how to design the cable crane and buckling-anchoring system, how to design the support frame used in section A of the arch rib, how to erect the work platforms, how to achieve measurement and controlling, how to adopt welding standard and mounting dimension standard, etc. , so as to provide reference for similar projects.关键词
钢管混凝土系杆拱桥/带副拱/中承式/菱形变截面/主拱肋/安装Key words
tied-arch bridge consisting of concrete-filled steel tubes/being accompanied with vice arch/half-through bridge/rhombic variable cross-section/main arch rib/installation分类
交通工程引用本文复制引用
潘寿东..带副拱中承式菱形变截面钢管混凝土系杆拱桥主拱肋安装技术[J].铁道标准设计,2014,(6):76-82,83,8.基金项目
中国铁道建筑总公司科技研究开发计划项目(09-26C)。 (09-26C)