确保 CSM 工法施工质量的措施
Measures to Ensure the Construction Quality of CSM Method
杨文华 1李江2
作者信息
- 1. 天津市地质基础工程公司,天津300191
- 2. 天津市滨海星城投资发展有限公司,天津300350
- 折叠
摘要
Abstract
CSM Method, that is double wheel milling deep mixing technology, is a new type of technology.A good job of the cement soil quality control and the related preparation work should be done to ensure the construction quality of CSM method before the construction.In construction process, the trenching verticality, cement in cement slurry, water cement ratio and grouting volume, milling drilling speed and double wheel revolution, overlapping length and quality of structural steel inserting must be under control.关键词
CSM工法/水泥土搅拌墙/施工质量控制/铣削/垂直度Key words
CSM Method/cement soil mixing wall/construction quality control/milling/verticality分类
建筑与水利引用本文复制引用
杨文华,李江..确保 CSM 工法施工质量的措施[J].探矿工程-岩土钻掘工程,2014,(6):63-65,71,4.