摘要
Abstract
Borehole wall protection is one of the key technologies for resolving drilling problems in Complex Strata.This pa-per introduces some special casing adopted in the drilling operation of the borehole WFSD-4, including large diameter cas-ing technology in small clearance condition, retrievable casing technology for small diameter core drilling in existing large borehole and two phase casing and cementing technology used in strong borehole shrinkage section.关键词
科学钻探/汶川地震断裂带/套管/护壁技术Key words
Scientific drilling/Wenchuan earthquake fault/casing/borehole分类
天文与地球科学引用本文复制引用