西北水电Issue(2):31-33,3.
麒麟寺水电站震后工程除险措施
Engineering Measures for Hazard Elimination of Qilingsi Hydropower Station after Earthquake
孙万林 1沈大伟 1王智琦1
作者信息
- 1. 中国水电顾问集团西北勘测设计研究院,西安 710065
- 折叠
摘要
Abstract
Issues, occurred after the earthquake happened o May 12, 2008, on Qilingsi Hydropower Station are analyzed and summa-rized.Corresponding handling measures and schemes are raised.In combination with the actual works, feasibility and safety of these schemes are calculated and studied.关键词
“5 .12”地震/工程除险/麒麟寺水电站Key words
earthquake happed on May 12, 2008/hazard elimination by engineering measures/Qilingsi Hydropower Station分类
建筑与水利引用本文复制引用
孙万林,沈大伟,王智琦..麒麟寺水电站震后工程除险措施[J].西北水电,2014,(2):31-33,3.