| 注册
首页|期刊导航|西北水电|山口水电站工程混凝土拱坝施工组织关键技术

山口水电站工程混凝土拱坝施工组织关键技术

李江 王健

西北水电Issue(2):39-44,6.
西北水电Issue(2):39-44,6.

山口水电站工程混凝土拱坝施工组织关键技术

Key Technology of Concrete Arch Dam Construction, Shankou Hydropower Project

李江 1王健2

作者信息

  • 1. 新疆水利水电规划设计管理局,乌鲁木齐市 830000
  • 2. 新疆水利水电勘测设计研究院,乌鲁木齐市 830000
  • 折叠

摘要

Abstract

Shankou Hydropower Project, with the total storage capacity of 2.22 million m3 , Grade 2B in scale, is located in the extremely cold and dry region, Xinjiang Autonomous Region.The water-retaining structure is the conventional concrete double-curvature dam with maximum height of 94 m.The dam concrete totally applies the fully graded aggregates.At the feasibility study stage, the key technical is-sues such as overflow cofferdam for river diversion, fully graded-aggregate concrete, dam concrete placement means and temperature con-trol, etc are studied in the construction method statement in combination with local climate, river diversion, flood control, four graded ag-gregates, landform conditions, etc.

关键词

严寒/双曲拱坝/导流/过水围堰/全级配/骨料/混凝土浇筑/温度/控制

Key words

extremely cold/double-curvature arch dam/river diversion/overflowing cofferdam/full gradation/aggregate/concrete place-ment/temperature/control

分类

建筑与水利

引用本文复制引用

李江,王健..山口水电站工程混凝土拱坝施工组织关键技术[J].西北水电,2014,(2):39-44,6.

西北水电

1006-2610

访问量0
|
下载量0
段落导航相关论文