水光互补电站建设分析

沈有国 祁生晶 侯先庭

西北水电Issue(6):83-86,4.
西北水电Issue(6):83-86,4.DOI:10.3969/j.issn.1006-2610.2014.06.021

水光互补电站建设分析

Analysis on Construction of Hybrid of Hydropower-Photovoltaic Power Plants

沈有国 1祁生晶 1侯先庭1

作者信息

  • 1. 黄河上游水电开发有限责任公司,西宁 810016
  • 折叠

摘要

Abstract

With practice of the on-grid photovoltaic power plant of the hybrid of Longyangxia Hydropower-Photovoltaic Power Plants, con-struction conditions and key points of the hybrid power plant are analyzed.By application of the regulating performance of the hydropower project, the photovoltaic power generation is optimized, providing the high-quality energy to the grid.

关键词

光伏电站/水光互补/运行协调/电气参数/电站出力

Key words

photovoltaic power plant/hybrid of hydropower and photovoltaic power/operation coordination/electric parameters/plant output