彭水水电站导流洞混凝土封堵施工
Plugging Construction of Diversion Tunnel, Pengshui Hydropower Project
高鄂湘 1王刚1
作者信息
- 1. 中国水利水电建设工程咨询西北有限公司,西安 710065
- 折叠
摘要
Abstract
During the construction of the permanent plug for the diversion tunnel of Pengshui Hydropower Project, leakage in a large quan-tity occurs at the transition section at the downstream of the Diversion Tunnel No.2 gate, resulting in water accumulated in the tunnel. The seepage flow is about 1.3 m3/s.Therefore, the temporary concrete plugs are proposed to build on both sides of the permanent plug to retaining the seepage so that the permanent plug can be constructed in dry condition.关键词
导流洞/封堵/施工法/综述/彭水水电站Key words
diversion tunnel/plugging/construction method/general description/Pengshui Hydropower Project分类
建筑与水利引用本文复制引用
高鄂湘,王刚..彭水水电站导流洞混凝土封堵施工[J].西北水电,2014,(6):97-100,4.