西北水电Issue(1):34-37,4.DOI:10.3969/j.issn.1006-2610.2015.01.009
公伯峡水电站进水口坝段基础水平位移监测值异常原因分析
Analysis on Causes of Abnormal Monitoring Data of Horizontal Displacement of Foundation at Power Intake Section, Gongboxia Hydropower Station
石广斌 1贾巍 2张曼曼3
作者信息
- 1. 西安建筑科技大学,西安 710054
- 2. 中国电建集团西北勘测设计研究院有限公司,西安 710065
- 3. 西安理工大学,西安 710048
- 折叠
摘要
Abstract
The power intake of Gongboxia Hydropower Station is of the water-retaining structure.After the reservoir is impounded and oper-ates, the monitoring data of the inverted plumb of the power intake No.5 are found abnormal.To analyze deeply the abnormal data which shows the displacement of the monitoring point of the inverted plumb at the power intake No.5 toward downstream is a little great, whether possibility of deep sliding resistance and causes of the greater displacement toward downstream are analyzed from the geological conditions of the foundation at the power intake dam section and with help of value method as well.关键词
公伯峡水电站/进水口/挡水建筑物/水平变形/异常Key words
Gongboxia Hydropower Station/power intake/water retaining structure/horizontal deformation/abnormal分类
建筑与水利引用本文复制引用
石广斌,贾巍,张曼曼..公伯峡水电站进水口坝段基础水平位移监测值异常原因分析[J].西北水电,2015,(1):34-37,4.