半导体封装测试生产线排产研究

姚丽丽 史海波 刘昶

自动化学报Issue(5):892-900,9.
自动化学报Issue(5):892-900,9.DOI:10.3724/SP.J.1004.2014.00892

半导体封装测试生产线排产研究

Research on Scheduling in Semiconductor Assembly and Test Manufacturing

姚丽丽 1史海波 2刘昶1

作者信息

  • 1. 中国科学院沈阳自动化研究所 沈阳 110016
  • 2. 中国科学院大学北京 100049
  • 折叠

摘要

Abstract

Taking one semiconductor assembly and test manufacturing (ATM) enterprise as the study object, this paper analyzes and summarizes the production process of ATM, and proposes a new model which is named capacity-limit flexible flow-shop (CLFFS) as the scheduling model of ATM. By researching on the special scheduling logic constraints, strategies, and rules of scheduling in ATM, we propose a forward heuristics algorithm which is controlled by both logic constraints and scheduling rules as the general method, and present a novel predictive control scheduling algorithm in batch-prepared one-processed stage. Finally, using the proposed model and method, an application example of scheduling in ATM and comparison are given. The results show that the general method has the effectiveness in practical application and can conveniently embed logic constraints, and that the novel predictive control scheduling algorithm can shorten production cycle and improve enterprise production benefit.

关键词

半导体封装测试/产能限定混线车间/启发式算法/正序排产

Key words

Semiconductor assembly and test manufacturing (ATM)/capacity-limit flexible flow-shop (CLFFS)/heuristic algorithm/forward scheduling

引用本文复制引用

姚丽丽,史海波,刘昶..半导体封装测试生产线排产研究[J].自动化学报,2014,(5):892-900,9.

基金项目

国家重大专项资助项目(2011ZX02601-005)资助 (2011ZX02601-005)

Supported by National Science and Technology Major Project of the Ministry of Science and Technology of China (2011ZX02601-005) (2011ZX02601-005)

自动化学报

OA北大核心CSCDCSTPCD

0254-4156

访问量3
|
下载量0
段落导航相关论文