基于两种瓶颈度的制造车间多瓶颈动态预测方法

刘志 蒋增强 龚本刚

中国机械工程Issue(14):1910-1915,1921,7.
中国机械工程Issue(14):1910-1915,1921,7.DOI:10.3969/j.issn.1004-132X.2014.14.013

基于两种瓶颈度的制造车间多瓶颈动态预测方法

Dynamic Prediction Method of Multi-bottleneck in Manufacturing Shop Based on Two Bottleneck Degrees

刘志 1蒋增强 2龚本刚1

作者信息

  • 1. 安徽工程大学,芜湖,241000
  • 2. 北京交通大学,北京,100044
  • 折叠

摘要

Abstract

Aiming at the prediction problem of multi-bottleneck in complex manufacturing shop , a dynamic prediction method of multi-bottleneck was proposed based on two bottleneck degrees ,which can forecast bottleneck accurately under conditions that bottleneck responsibility was verified reasona-bly .Firstly ,conceptual models about general bottleneck degree and independent bottleneck degree were built ,and then taking time ,quality and cost as parameters ,their mathematical models were es-tablished .Secondly ,one dynamic prediction method of multi-bottleneck was come up with ,which con-tained dual-layer multi-bottleneck prediction mechanism ,bottleneck polymorphism analysis and the it-erative prediction of bottleneck index .Finally ,it is proved to be superior and credible by comparison to the method of single bottleneck degree and the method of PBM for production bottleneck prediction problem of one vehicle assembly line .

关键词

多瓶颈/瓶颈责任/综合瓶颈度/独立瓶颈度/动态预测

Key words

multi-bottleneck/bottleneck responsibility/general bottleneck degree/independent bot-tleneck degree/dynamic prediction

分类

机械制造

引用本文复制引用

刘志,蒋增强,龚本刚..基于两种瓶颈度的制造车间多瓶颈动态预测方法[J].中国机械工程,2014,(14):1910-1915,1921,7.

基金项目

国家自然科学基金资助项目(71171002);中央高校基本科研业务费专项资金资助项目(2012JBM090);安徽高校省级自然科学研究项目(K J2013B033);安徽高校省级人文社会科学研究项目 ()

中国机械工程

OA北大核心CSCDCSTPCD

1004-132X

访问量0
|
下载量0
段落导航相关论文