原子能科学技术Issue(9):1655-1659,5.DOI:10.7538/yzk.2015.49.09.1655
秦山第二核电厂1 & 2号机组主蒸汽安全阀改进分析
Analysis of Main Steam Safety Valve Improvement for Qinshan Nuclear Power Plant Phase 2 Unit 1 & 2
任春明 1陈坚刚 2黄代顺3
作者信息
- 1. 中国核动力研究设计院,四川 成都 610041
- 2. 中国核动力研究设计院 核反应堆系统设计技术重点实验室,四川 成都 610041
- 3. 中核核电运行管理有限公司,浙江 海盐 314300
- 折叠
摘要
Abstract
An improvement for Qinshan Nuclear Power Plant Phase 2 unit 1&2 ,in which the power‐operated valves are replaced with the spring‐loaded valve with setpoint adjustment for the 1st group safety valves of steam generators ,would be adpoted on the basis of comparison with similar improvement implemented in Qinshan Nuclear Power Plant Phase 2 unit 3&4 .The feasibility was evaluated from several aspects ,including mechanical design ,instrument & control design and safety analysis .On the premise of guaranteeing safety ,this improvement can simplify design ,observably reduce project costs and avoid increasing the potential probability of the reactor trip risk induced by complication of the system and control logic .关键词
秦山第二核电厂/主蒸汽安全阀/改进Key words
Qinshan Nuclear Power Plant Phase 2/main steam safety valve/improve-ment分类
能源科技引用本文复制引用
任春明,陈坚刚,黄代顺..秦山第二核电厂1 & 2号机组主蒸汽安全阀改进分析[J].原子能科学技术,2015,(9):1655-1659,5.