| 注册
首页|期刊导航|电力勘测设计|高位收水冷却塔集水槽结构设计

高位收水冷却塔集水槽结构设计

何磊 黄涛 陈绍林

电力勘测设计Issue(3):37-41,5.
电力勘测设计Issue(3):37-41,5.

高位收水冷却塔集水槽结构设计

Structure Design of Water Reservoir for Cooling Tower with High-collected Water

何磊 1黄涛 1陈绍林1

作者信息

  • 1. 西南电力设计院,四川成都 610021
  • 折叠

摘要

Abstract

The cooling tower with high-collected water has obvious energy-saving advantage, which shall be broad application prospects in the millions of units for the thermal power plant. The water reservoir is a basin for recycling the circulating cooling water of cooling tower with high-collected water. The safe and reliable structural design for water reservoir has a important role in the safe operation of thermal power plant. In this paper, the water reservoir was simulated and calculated by theifnite element software ANSYS, its result was applied to structure design. The method is obvious advantage in technology and economy, which shall be referred by the similar project.

关键词

高位收水冷却塔/集水槽/结构设计/有限元仿真计算

Key words

cooling tower with high-collected water/water reservoir/structure design/ifnite element simulative analysis

分类

信息技术与安全科学

引用本文复制引用

何磊,黄涛,陈绍林..高位收水冷却塔集水槽结构设计[J].电力勘测设计,2015,(3):37-41,5.