岩土工程学报Issue(z1):17-24,8.DOI:10.11779/CJGE2014S1003
杭州钱江新城金融地块不对称超深基坑支护设计研究
Design of supports for asymmetric extra-deep foundation pit of financial block project in Qianjiang CBD of Hangzhou
杨学林 1曹国强 1周平槐1
作者信息
- 1. 浙江省建筑设计研究院,浙江 杭州 310006
- 折叠
摘要
Abstract
The deep foundation pit is located in Qianjiang CBD of Hangzhou City and is less than 100 m away from the Qiantang River. It's well known as the high water level and strong permeability foundation. There are four dependent high-rise towers on the ground which belong to 4 bank finacial units respectively, and a large integral basement consists of three parts, three-story basement under the towers of Huarong and ICBC (Industrial and Commercial Bank of China Limited), four-story basement under the commercial tower and five-story basement under the tower of China Zhejiang Bank Co., Ltd. The excavation depth is in the range of 17.0~24.0 m, and the maximum depth is approximately 28.5m in the core tube. In addition, the overview and features, retaining schemes, excavation process under the conditions of asynchronic construction, measures of dismantling and replacing support, analysis of the internal force and deformation caused by asymmetric excavation, treatment of deep confined water and monitoring results are introduced.关键词
超深基坑/不对称开挖/不同步施工/强渗透性地基/拆撑与换撑/深层承压水处理Key words
extra-deep foundation pit/asymmetric excavation/asynchronous construction/strong permeability foundation/dismantling and replacing support/treatment of deep confined water分类
建筑与水利引用本文复制引用
杨学林,曹国强,周平槐..杭州钱江新城金融地块不对称超深基坑支护设计研究[J].岩土工程学报,2014,(z1):17-24,8.