古滑坡体上的挖填方路基边坡设计方案研究
Study of Cut-and-fill Roadbed Engineering Design and Construction on an Ancient Landslide Mass
吴震1
作者信息
- 1. 中国中铁二院工程集团有限责任公司,成都 610031
- 折叠
摘要
Abstract
It is very difficult to make a cut-and-fill slop engineering on an ancient landslide mass. An engineering example was used to study in this aspect. Wudang Section K8+200~+540 of Guiyang Shidong road gets through an ancient landslide mass aera. According to the site condition, a road shoulder protecting wall supported by pile foundation conbined with anchor rope retaining slab wall was adopted in the design plan, meanwhile, some monitoring measures were used in construction, such as, controlling the pile top displacement, adopting proper pile size and length and smart construction style, etc. By four years’ use, the roadbed is stable, the ancient mass is stable, the construction term is shorted and lots of cost are saved.关键词
古滑坡体/路基边坡工程/设计与施工方法Key words
Roadbed engineering/ancient landslide mass/design and construction ways分类
交通工程引用本文复制引用
吴震..古滑坡体上的挖填方路基边坡设计方案研究[J].交通运输工程与信息学报,2013,(2):31-36,64,7.