摘要

Abstract

A number of karst caves were developed in partial sections of No .3 and 4 diversion tunnels of Jinping Hydropower Station, in which, a large-scale karst cave was exposed during the floor excavation of No .3 diversion tunnel.To ensure the safety of the tunnel operation , on the basis of the analysis of the characteristics of the large karst cave exposed in excavation , the reinforcement measures of fresh concrete backfilling and arch bridge were adopted , and the well-pile-beam was used for the first time in tunnel construction .A detailed introduction to the construction process and treatment measures is given to provide reference for other similar projects .

关键词

引水隧洞/岩溶/软基处理/锦屏水电站

Key words

diversion tunnel/karst/soft foundation treatment/Jinping Hydropower Station