人民长江Issue(22):88-90,94,4.DOI:10.16232/j.cnki.1001-4179.2015.22.020
锦屏二级水电站筒阀动水关闭试验及仿真分析
Experiment of dynamic closing process of cylindrical valve at Jinping Power Station II and simulation analysis
汪德楼 1方杰 1吴胜华 1黄靖乾 1曹春建1
作者信息
- 1. 中国电建集团 华东勘测设计研究院有限公司,浙江 杭州310014
- 折叠
摘要
Abstract
In order to test the actual operation condition of cylindrical valve in hydro-power station with long-distance water delivery system, the change of state variables of the unit under partial load in the dynamic closing process of the cylindrical valve was detected by the field test method. The dynamic closing process of cylindrical valve was simulated numerically on the basis of the test data. The comparison results showed that the two were highly consistent, which proved the accuracy of the numerical sim-ulation. The prediction for the extreme modes of cylindrical valve closing process by the numerical simulation method indicated that the pressure at the inlet of the spiral case in 100% load met the requirements of the contract. It provides basis for ensuring the safe operation of mechanical and electrical equipment of hydropower stations.关键词
筒阀/关闭规律/数值模拟/极值预测/误差修正Key words
cylindrical valve/closing law/numerical simulation/extreme value forecast/error correction分类
建筑与水利引用本文复制引用
汪德楼,方杰,吴胜华,黄靖乾,曹春建..锦屏二级水电站筒阀动水关闭试验及仿真分析[J].人民长江,2015,(22):88-90,94,4.