探矿工程-岩土钻掘工程Issue(4):27-30,4.
伊朗雅达油田首口水平井 S15钻井技术
Drilling Technology for the First Horizontal Well S15 in Yada Oilfield of Iran
庞元平 1李蕾 1李楠2
作者信息
- 1. 中国石化胜利钻井工程技术公司,山东东营257064
- 2. 中国石油勘探开发研究院,北京100083
- 折叠
摘要
Abstract
S15 well is located in the southeast of Ahawaz in Iran, which was a sidetracking horizontal well and the first hori-zontal well by Sinopec in Yada project in Iran.Because of the long open hole section, deep sidetrack points, long horizontal section and large horizontal displacement, the construction was very difficult.In order to ensure the smooth progress of the construction, aimed at the characteristics of drilled formation, through making up the effective trajectory control scheme, selecting the appropriate screw and BHA, taking reasonable drilling parameters and technical measures and meanwhile opti-mizing the drilling tool structure, the drilling tasks were successfully completed.The matching horizontal well drilling tech-nologies suitable to Yada of Iran were summed up as the reference for the late horizontal wells drilling construction.关键词
S15井/轨迹控制/侧钻水平井/螺杆/伊朗雅达油田Key words
S15 well/trajectory control/sidetracking horizontal well/screw/Daya oilfield in Iran分类
石油、天然气工程引用本文复制引用
庞元平,李蕾,李楠..伊朗雅达油田首口水平井 S15钻井技术[J].探矿工程-岩土钻掘工程,2013,(4):27-30,4.