西北水电Issue(5):58-60,3.DOI:10.3969/j.issn.1006-2610.2015.05.017
桃源电站贯流式机组主轴密封安装工艺优化
Optimization of Installation of Main Shaft Sealing of Tubular Turbine-generato r Unit
潘军伟 1姜明忠 2张占武2
作者信息
- 1. 中国水电顾问集团风电隆回有限公司,湖南省邵阳市 422200
- 2. 中国水利水电第三工程局有限公司,西安 710032
- 折叠
摘要
Abstract
Structure, operating principle and installation technology requirements, etc of the main shaft sealing of the bulb tubular unit in Taoyuan Hydropower Station are described.The installation technology of certain key positions is optimized.The optimization results in sig-nificant achievement.It can be referred to the sealing installation and maintenance of the similar power stations.关键词
主轴密封/结构型式/工作原理/安装工艺Key words
sealing of main shaft/structural type/operation principle/installation technology分类
能源科技引用本文复制引用
潘军伟,姜明忠,张占武..桃源电站贯流式机组主轴密封安装工艺优化[J].西北水电,2015,(5):58-60,3.