| 注册
首页|期刊导航|云南水力发电|大型水电站厂房三维设计研究与应用

大型水电站厂房三维设计研究与应用

杨小龙 吴贵春

云南水力发电Issue(5):132-134,138,4.
云南水力发电Issue(5):132-134,138,4.DOI:10.3969/j.issn.1006-3951.2015.05.037

大型水电站厂房三维设计研究与应用

Study and Application of the 3-dimensional Design of Large Hydropower Project Powerhouses

杨小龙 1吴贵春1

作者信息

  • 1. 中国电建集团昆明勘测设计研究院有限公司,云南 昆明 650051
  • 折叠

摘要

Abstract

The paper deals with the study of the problems existing in the application of Autodesk Revit 3-dimensional design software to the 3-diemensional design of a large hydropower plant powerhouse, The study results have been put into effect so that the whole process of establishment of 3-dimensional module→structural CAE analysis→multi-speciality coordinated design→completion of 3-dimensional drawing of the 3-dimensional design of a hydropower plant powerhouse could be implemented. The secondary development of the 3-dimensional reinforcement drawing-making accessory system of a large size complex structure lays the foundation of the follow-up design of a hydropower plant powerhouse in terms of establishment of a parameterized model library and a standardized sample document and pixel library and improvement of designing efficiency and product quality and service.

关键词

三维设计/协同设计/CAE数据接口/三维钢筋/样板文件/三维出图

Key words

3-dimensional design/coordinated design/CAE data interface/3-dimensional reinforcement/sample document/3-dimensional drawing-making

分类

建筑与水利

引用本文复制引用

杨小龙,吴贵春..大型水电站厂房三维设计研究与应用[J].云南水力发电,2015,(5):132-134,138,4.

云南水力发电

1006-3951

访问量0
|
下载量0
段落导航相关论文