| 注册
首页|期刊导航|海河水利|句容抽水蓄能电站地下厂房洞室群支护措施研究

句容抽水蓄能电站地下厂房洞室群支护措施研究

胡正凯 李良权 姚新刚

海河水利Issue(6):55-58,4.
海河水利Issue(6):55-58,4.DOI:10.3969/j.issn.1004-7328.2015.06.019

句容抽水蓄能电站地下厂房洞室群支护措施研究

Research of Support Measures for the Underground Caverns at Jurong Pumped Storage Power Plant

胡正凯 1李良权 1姚新刚1

作者信息

  • 1. 中国电建集团华东勘测设计研究院有限公司,浙江 杭州 310014
  • 折叠

摘要

Abstract

For the complicated engineering geological conditions of underground caverns at Jurong Pumped Storage Power Plant,reference to supporting design experience of similar projects,flexible support system designed to shotcrete and an-chor support mainly to develop three different support measures schemes. Using 3DEC mathematical model,based on the model of the underground caverns different support schemes were analyzed by the surrounding rock deformation,stress and plastic zone characteristics terms of comparison,considering various factors combined project investment,construction pe-riod,construction,and ultimately determine the reasonable support measures for the underground powerhouse caverns.

关键词

抽水蓄能电站/地下厂房洞室群/支护措施/围岩稳定

Key words

pumped storage power plant/underground caverns/support measures/surrounding rock stability

分类

建筑与水利

引用本文复制引用

胡正凯,李良权,姚新刚..句容抽水蓄能电站地下厂房洞室群支护措施研究[J].海河水利,2015,(6):55-58,4.

海河水利

1004-7328

访问量0
|