运筹与管理2016,Vol.25Issue(1):25-34,10.DOI:10.12005/orms.2016.0004
基于融资能力约束的多模式 Max-npv 项目调度优化:双重视角
Financing Capacity Constraint Based Multimode Max-npv Project Scheduling Optimization from Both Perspectives of Contract
摘要
Abstract
This paper deals with the multimode Max-npv project scheduling problem with financing capacity constraints from the two sides of contract .The authors define the studied problem at first and then , construct the optimization model which consists of the client ’ s and the contractor ’ s submodels .Due to the strong NP-hardness of the problem , a tabu search heuristic , which solves the two submodels iteratively , is developed , thus obtaining the desirable solution which can be accepted by contractor and client simultaneously .Ultimately , a practical pro-ject is utilized to illustrate the research and through analyzing the key parameters of the instance , the following conclusions are drawn .The theoretical desirable schedule can increase the profits of the contractor and the client in the meantime .The key parameters including the client ’ s and the contractor ’ s financing capacity , the project deadline , the baseline profit of the contractor , the discount rate and the payment proportion all influence the parties’ project npv.关键词
Max-npv项目调度/双重视角/优化模型/禁忌搜索/融资能力约束Key words
Max-npv project scheduling/two perspectives of contract/optimization model/tabu search/financing capacity constraints分类
管理科学引用本文复制引用
郑维博,何正文,刘人境..基于融资能力约束的多模式 Max-npv 项目调度优化:双重视角[J].运筹与管理,2016,25(1):25-34,10.基金项目
国家自然科学基金资助(项目名称风险环境下大型复杂工程项目现金流动态均衡调度优化研究,项目编号71371150);新世纪优秀人才支持计划资助 ()