| 注册
首页|期刊导航|铁道标准设计|下穿河道和桥梁基础的某地铁车站设计方案探讨

下穿河道和桥梁基础的某地铁车站设计方案探讨

闫继龙

铁道标准设计2016,Vol.60Issue(5):116-120,5.
铁道标准设计2016,Vol.60Issue(5):116-120,5.DOI:10.13238/j.issn.1004-2954.2016.05.025

下穿河道和桥梁基础的某地铁车站设计方案探讨

Discussion on Design of a Metro Station Passing Underneath Riverway and Bridge Foundation

闫继龙1

作者信息

  • 1. 中铁工程设计咨询集团有限公司郑州设计院,郑州 450001
  • 折叠

摘要

Abstract

Based on the Nanning subway Line 1 , the station of Shibu is designed to pass underneath Shibu river and its bridge foundation. Due to the constraint of engineering conditions, the cut-and-cover method is adopted to resolve three design problems including river diversion, foundation ditch support and re-construction of bridges. According to the in-situ circumstances, the correlation between the three is analyzed, and an integrated design scheme is proposed, which is composed of cofferdam plus diversion by draft tube, anchor cable plus internal support system and construction of bridges with box girder. Subsequently, the specific design approach is introduced and the main points of design for each item are put forward. The construction of the metro station and re-construction of bridges are successfully implemented due to the application of this design scheme and the designed flood carrying capacity is guaranteed, which demonstrates the rationality and feasibility of the scheme.

关键词

地铁车站/河道导流/基坑组合支护/桥梁还建

Key words

Subway station/River diversion/Composite support of foundation pit/Re-construction of bridges

分类

交通工程

引用本文复制引用

闫继龙..下穿河道和桥梁基础的某地铁车站设计方案探讨[J].铁道标准设计,2016,60(5):116-120,5.

铁道标准设计

OA北大核心

1004-2954

访问量0
|
下载量0
段落导航相关论文