摘要
Abstract
In the construction of drilled cast-in-place pile foundation under the coal silo of Huanghua Coal Terminal Phase-3 project, post-grouting technology is adopted to renovate the quality defects existed in the construction of large-diameter drilled cast-in-place piles,such as settled material at the bottom of pile and thicker mud coat at the side of pile, which can increase the bearing capacity of pile foundation to a large extent. Now the principle of work, construction key points and the measures to deal with common problems are introduced in detail for post-grouting method strengthening the bearing capacity of pile foundation,which will provide references for similar projects.关键词
大直径钻孔灌注桩/注浆法/后注浆法/桩基承载力Key words
large-diameter drilled cast-in-place pile/mud-jack method/mud-inject method/bearing capacity of pile foundation分类
交通工程