In the process construction of the high -rise buildings pit,because of the excavation,load increase and the mechanical shock Etc,lead to the pit de-formation,even col apse.Based on the set lement and displacement monito-ring of the terminal ,we can master the regular pat ern of the terminal set le-ment and placement deformation along with the time .Thus provide the reli-able datas for construction and operation safety.This paper take the pit Set-tlement and placement observation for example,analysis the monitoring pro-gramme design,the observation points set ing ,the Set lement observation, the displacement observation and the data results submit ed.关键词
深基坑/基准点/观测点/沉降观测/水平位移观测Key words
Deep pit/The benchmark points/The observation points/The Set le-ment observation/The displacement observation