山东煤炭科技Issue(8):25-26,29,3.DOI:10.3969/j.issn.1005-2801.2016.08.012
深部矿井准备巷道联合布置设计优化
Design optimization of combined arrangement for deep mine roadway
房博 1王明 1宁廷洲1
作者信息
- 1. 山东能源新矿集团华丰煤矿,山东新汶 271413
- 折叠
摘要
Abstract
The deep preparation roadway in HuaFeng coal mine, is excavated in the whole rock , which has a long preparation time and high cost. The expansion of completed the expanded level roadway with large section was used as the comprchensive transportation roadway, which cancel the convoy transportation roadway, implement the transport material, coal concentration, simplify the preparation of engineering, ease the mining continuing, and reduce million-ton drivage rate.关键词
准备巷道/联合/布置/优化Key words
preparation roadway/comprchensive/combined arrangement/design optimization分类
矿业与冶金引用本文复制引用
房博,王明,宁廷洲..深部矿井准备巷道联合布置设计优化[J].山东煤炭科技,2016,(8):25-26,29,3.