山东煤炭科技Issue(8):27-29,3.DOI:10.3969/j.issn.1005-2801.2016.08.013
全锚巷道沿空留巷数值模拟研究
Numerical Simulation of Gob-side Entry Retaining for Bolting Entry
石彦磊 1李宗岑2
作者信息
- 1. 平煤股份四矿,河南 平顶山 467093
- 2. 中国矿业大学,江苏 徐州 221008
- 折叠
摘要
Abstract
The loading process of F15-31020 belt conveyor entry in No.4 Colliery of Pingdingshan Coal Group Company was carried out with FLAC3D. The results showed that convergence between roof and floor and convergence between two sides was respectively 0.8 m and 0.9 m during the ifrst mining inlfuence, and the former two was respectively 1.1 m and 1.05 m during the second mining inlfuence. The numerical simulation result shows that gob-side entry retaining of F15-31020 belt conveyor entry is practicable.关键词
沿空留巷/一次采动/二次采动/数值模拟Key words
gob-side entry retaining/first mining inlfuence/second mining inlfuence/numerical simulation分类
矿业与冶金引用本文复制引用
石彦磊,李宗岑..全锚巷道沿空留巷数值模拟研究[J].山东煤炭科技,2016,(8):27-29,3.