广东电网500 kV机组改接接入220 kV电网的相关问题研究

邓婧

机电工程技术2016,Vol.45Issue(10):146-149,4.
机电工程技术2016,Vol.45Issue(10):146-149,4.DOI:10.3969/j.issn.1009-9492.2016.10.033

广东电网500 kV机组改接接入220 kV电网的相关问题研究

Integration of Generation Unit Reconnected from 500kV Power Grid to the 220kV

邓婧1

作者信息

  • 1. 中国能源建设集团广东省电力设计院有限公司,广东广州 510600
  • 折叠

摘要

Abstract

In order to relieve the insufficient of 500kV down capacity,reduce the pressure of 500kV transformer substation,enhance the safety and reliability of 220kV power grid, except speeding up the 500kV transformer substation setting and its accessional 220kV project, reconnecting generation unit from 500kV power grid to the 220kV is also the scientific and effective method. Investigate the generation units connected to 500kV voltage in Guangdong power grid,study them from reconnected demand,reconnected plan economy and feasibility, propose the generation grid which need to reconnect. It is also helpful to promote the implementation of practical reconnected project.

关键词

220 kV电网/500 kV降压容量/改造需求/改造时机

Key words

220 kV power grid/500 kV down capacity/reconnected demand/reconnected time