人民长江2016,Vol.47Issue(22):51-54,59,5.DOI:10.16232/j.cnki.1001-4179.2016.22.010
复杂岩溶区深埋长隧洞线路比选优化实践
Optimization of route selection for deep buried long tunnel in complex karst area
张海平 1王家祥 1刘承新 1陈长生 1李银泉1
作者信息
- 1. 长江三峡勘测研究院有限公司 武汉,湖北 武汉430074
- 折叠
摘要
Abstract
In the construction of deep buried long tunnel in complex karst region, geological disasters such as water burst, wa-ter inrush, mud burst and so on are prone to occur and may lead to a series of groundwater environmental problems. Therefore, the tunnel should be constructed in non ( or weak) karst area to minimize the drainage of groundwater. Taking a deep buried long tunnel in complex karst area of water diversion project in central Yunnan Province as an example, we judged the development de-gree of the deep karst on macro scale and defined the accurate position of underground watershed in the study area based on hydrological and engineering geological survey and mapping, together with technical methods of drilling, groundwater tracer test and earth electromagnetic sounding. The results provided a reasonable, accurate and feasible basis for the optimization of tunnel route .关键词
复杂岩溶区/深埋长隧洞/钻探/地下水示踪试验/大地电磁测深Key words
complex karst area/deep buried long tunnel/drilling/earth electromagnetic sounding/groundwater tracing test分类
天文与地球科学引用本文复制引用
张海平,王家祥,刘承新,陈长生,李银泉..复杂岩溶区深埋长隧洞线路比选优化实践[J].人民长江,2016,47(22):51-54,59,5.